Turnkey Projects
TOOT MNE TECH PVT LTD is registered as a Class I Electrical Contractor and has earned a good name in its domain in the industry. We specialize in turn-key projects and undertake all types of electrical contacts in industries, substations, residential and commercial complexes, banks, IT Parks, shopping malls, educational institutes, hotels, and government organizations.
Types of Projects We Undertake :
We are rather selective and agree only for those turn-key projects where we feel we can deliver to the client as per his desired specification and to his full satisfaction. Most of the projects we undertake pertain to Substation Work, Electric Panels, Internal and External Electrification, LT & HT Cabling and Termination, Overhead Transmission Lines, Overhead Transmission Towers, Main and Sub-main Switch Boards, Earthing, Street Lighting, Flood Lighting, Lighting in Parks, Instrumentation System, Communication System, Fire Fighting System, Cable Design and Routing, Cable Tray and Trunking, Installation & Commissioning of Diesel Sets, Transformers and UPS Systems, Air-conditioning, Networking, Data Center Infrastructure, and Energy Auditing, Monitoring and Conservation, etc. Apart from these we also undertake Operation and Maintenance Works for Long Term Performance. We have all measuring and test equipment required for inspection, calibration, and testing of installations at the site. Most important is that we also liaison with Electricity Board from beginning to end-stage for satisfactory work completion.
Main Features of Our Services :
- Design and conceptualization based on customer's conceptual design and specifications
- Preparation of bill of quantities, tendering
- Preparation of detailed drawings, site set out
- Sourcing of material
- Marking and execution in accordance with the design
- Obtaining finished levels
- Evaluation and submission of progress report
- Execution of planting schemes
- Total commissioning
Procedure For Laying Down LT & HT Cables :
Given below is a brief outline of the approach and precautions we normally take for laying down LT/HT cables.
Storage of Cable Drums :
- We store the cable drums on a well-drained and hard surface.
- For long terms storage, these drums are covered with tarpaulin, and both ends of the cable are sealed.
- If required, we also roll these through 90o
Selection of Cables :
- In general, we prefer to use PVC/XLPE insulated and PVC sheathed cables.
- For very high voltage (from 11KV to 33KV) we prefer cables with the solid or stranded Aluminum conductor; Copper conductor can be used only in special applications where the use of Aluminum conductor is not technically acceptable.
- We prefer only those multi-core cables that are properly armored to prevent any kind of mechanical damage.
Safety Precautions :
- Where necessary, we display a caution board indicating CAUTION - CABLE JOINTING WORK IN PROGRESS to warn the public and traffic.
- Before starting jointing, we take all safety precautions like isolation, discharging, earthing, display of caution board on the controlling switchgear, etc. to ensure that the cable would not be inadvertently charged from the live supply.
Cable Handling and Laying :
- We ensure that both ends of the cable are properly sealed to prevent ingress/absorption of moisture.
- Even for short distances, we roll the cable drums in the direction of the arrow marked.
- Before we remove the cable from the drum, we mount the latter properly on jacks or cable wheels.
- Our cabling does not have sharp bends. Instead, we make the bends rounded at corners to a radius not lesser than 12 times the overall diameter of the cable, thereby avoiding any damage to cables.
- We avoid taking a risk and discard defective cables like those with sharp bends and defective armoring etc
- We dig separate trenches for power and control cables. But if that be not possible for any reason, we lay first HV cables and over that the LV cables with adequate separation.
- We lay down power and communication cables at right angles or give clearance of a minimum of 60 cm.
- We always try to avoid waterlogged locations, carriage-ways, payments, areas in proximity to telephone cables, gas and water mains, inaccessible places, etc.
- In areas where there is a chance of damage to wiring/cables, we always provide a proper metallic protective covering.
- While cutting and stripping the outer sheathing of the cable, we always take the utmost care not to allow the sharp edge of the cutting instrument to touch the inner insulation of the conductor.
Cable Jointing & Termination :
- Prior to laying down cables, we decide about ideal locations for proposed joints. As far as possible, we try to avoid waterlogged locations, carriageways, pavements, proximity to telephone cables, gas or water mains, inaccessible places, ducts, pipes, and racks, etc.
- When joints are to be done for two or more cables laid together in the same trench, we stagger these by 2m to 3m.
- We keep the cable joints in suitable and approved cable joint boxes, making sure that these do not allow entry of moisture. We also try to leave about 3m long surplus cable on each side of the joints.
- We give preference to heat shrinkable joints that have high insulation at jointing ends. In any case, we always ensure that there is a solid connection between the metal conductor and terminating clip.
- Our cables are terminated on to the terminals of switchgear through heavy-duty crimping lugs of proper size.
- In order to maintain continuity of cable armoring, we use double compression glands and proper crimping tools.
- In Aluminum cables exposed to the outside atmosphere, we remove the oxide film before joining.
Trenching & Cable Laying :
- Our trenches for cable laying are straight or with suitable curvatures and with changes in depth gradient being gradual. These have a minimum width of 45 cm and a depth of 75 cm. The bottom of the trench is always kept free of stones and bricks.
- When there is more than one cable in a single trench, we ensure that these are kept at a distance.
- We give a minimum of 9 cm dry sand cushion below and above the cables. Over the topmost layer of sand cushion, we put one layer of bricks as an extra protective covering, and over that put back the excavated soil free from stones and debris. In order to avoid the chances of any waterlogging, our trenches have about 10 cm hump on top with tapering on sides.
- At entry/exit cable points into the building, we pass the cables through pipe sleeves, which are properly sealed to prevent the entry of any seepage water.
- Our manholes are large enough to have sufficient working space and for feeding/drawing of cables.
- We always leave sufficient cable loop length that is a must.
Manholes :
Our manholes are watertight, made with first-class bricks, having a top slab of RCC, concrete foundation and cement plastering both inside and outside, and neatly finished.
Cable Trays :
We use MS cable trays that are strong enough and rust/corrosion-free. Whether these should be hot-dip galvanized or painted is decided based on location. Likewise whether to use perforated or ladder-type cable trays would depend on cable load. These cable trays are then joined together using bends, joints, coupler plates, and other accessories as may be required to have a complete and fully functional cable tray system. Where necessary, we give an additional coat of zinc-rich paint.
In normal dry weather, we keep the Megger value at 50 Mega Ohm. Apart from this we also conduct the following tests.
- Insulation resistance test
- Continuity resistance test
- Sheathing continuity test
- Earth test (in armored cables)
- Hi-Pot test
E also tests on-site for insulation between phases and between phase and earth for each length of cable, before and after joining. After cable laying down has been completed, we carry out the following tests in presence of the owner's representative.
- Insulation resistance test (sectional and overall)
- Continuity resistance test
- Sheathing continuity test
- Earth test
- High voltage test (only in case of HT cables)
Cable Tags :
- We give proper marking to each cable in all critical places using Aluminum cable tags of sufficient thickness and size.
Maintenance Free Chemical Earthing :
Maintenance-free chemical earthing is done strictly as per the manufacturer's recommendations. However, we try to ensure that it is of good quality, completely maintenance-free, has a long life of close to 25years, environmentally safe, non-corrosive, and electrically conductive. The earth resistance should not be less than one ohm.